YMCA expansion (Terre Haute)

Construction expansion of the Terre Haute YMCA, general contractor Garmong. Subject of a July 2026 dispute over responsible-bid ordinance compliance; the Board of Public Works and Safety approved a third contract amendment (GMP 3) on Aug. 24, 2026, creating an $83,000 owner-contingency fund.

Also known as: YMCA expansion · Garmong YMCA project · GMP 3 · GMP3 amendment · owner contingency fund